Question No : 196) A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
A. Process diagram
B. Change control plan
C. Balanced scorecard
D. SWOT matrix
Question No : 197) A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
A. Team Building
B. Team Selection
C. Resource loading
D. Resource leveling
Question No : 198)Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A. Determine the flexibility between the project constraints
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register
Question No : 199) Which of the following project phases occurs when requirements are detailed?
A. Initiation
B. Monitor and control
C. Planning
D. Closing
Question No : 200) Given the information in the table below, which of the following is the total project cost?
A. $40,000
B. $70,000
C. $95,000
D. $120,000
Question No : 201) The final project report should contain which of the following?
A. Minutes of all the project meetings
B. Project design documentation
C. Detailed breakdown of the schedule
D. Summary of the project cost
Question No : 202) A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST appropriate for the project manager to do NEXT?
A. Refer to the contingency plan
B. Conduct an immediate emergency team meeting
C. Perform a SWOT analysis
D. Implement the risk response plan
Question No : 203) Which of the following project phases would MOST likely include a creating transition plan?
A. Closing
B. Initiation
C. Execution
D. Planning
Question No : 204) Which of the following is a characteristic of a project?
A. It solves a business problem.
B. It created a unique service.
C. It has a definite beginning and end.
D. It adheres to a formal framework.
Question No : 205) A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
A. Projectized
B. Balanced matrix
C. Functional
D. Strong matrix
Question No : 206) A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The projectmanager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
A. change management
B. A milestone
C. a tollgate
D. an incident response
Question No : 207) A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?
A. Requirements traceability matrix
B. Gantt chart
C. SWOT analysis
D. Project charter
Question No : 208) At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
A. Team contract
B. Corrective action plan
C. User acceptance policy
D. MOU
E. SLA
Question No : 209) Based on the table below:
Which of the following is the critical path if Task B has extended to ten days?
A. 21 days
B. 23 days
C. 24 days
D. 26 days
Question No : 210) When developing a project schedule, which of the following tools would be MOST beneficial?
A. Gantt chart
B. Network diagram
C. Fishbone chart
D. Chain diagram
PK0-005 Answers