Question No : 241) The Chief Executive Officer (CEO) has changed the direction of a business and no longer needs one of the divisions. A deal is reached to sell the division to a company in another state. Which of the following BEST describes this type of organizational change?
A. Business process change
B. Internal reorganization
C. Relocation
D. Demerger
Question No : 242) Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue?
A. Risks were not identified.
B. Risks were not mitigated.
C. Risks were not exploited.
D. Risks were not communicated.
Question No : 243) Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
A. Critical Path Method
B. Arrow Diagramming Method
C. Critical Chain Method
D. Precedence Diagramming Method
Question No : 244) Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks:Task Duration
A) Four weeks
B) Two weeks
C) Six weeks
D) Three weeks
E) Seven weeks
F) One week
G) Two weeks
H) Nine weeks
Which of the following tasks are on the critical path?
A. A, D, C, G
B. A, B, H, G
C. A, D, E, F
D. A, B, C, G
Question No : 245) A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?
A. RACI
B. SWOT
C. SOW
D. WBS
Question No : 246) Which of the following describes some of the features of the Agile methodology?
A. It uses a direct approach, Gantt charts, and a ticketing system.
B. It uses an indirect approach, spreadsheets for documentation, and change request documents.
C. It uses an iterative approach, backlogs, and burndown charts.
D. It uses a step-by approach, an issue log, and pie charts.
Question No : 247) A project manager needs status on the project timeline. Which of the following team members should provide an update?
A. Product owner
B. Business analyst
C. Scheduler
D. Sponsor
Question No : 248) A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
A. Incident response
B. Quality control
C. Resource changes
D. Business continuity response
Question No : 249) When an action is taken on a risk, which of the following is being done and which document needs to be updated?
A. Mitigating risk, and the risk register should be updated
B. Accepting risk, and the risk review document should be updated
C. Avoiding risk, and the risk review document should be updated
D. Exploiting risk, and the risk register should be updated.
Question No : 250) A new corporate policy was approved that will positively affect the project. Which of the following should the project manager do FIRST?
A. Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register
Question No : 251) Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?
A. Encrypted email
B. Face-to-face communication with a translator
C. Social media communication through a secure connection
D. Voice conferencing
Question No : 252) Which of the following describes a project’s budget overrun?
A. The project spends only half of the funds.
B. The project spends only the allocated funds.
C. The project spends none of the funds.
D. The project spends in excess of the funds.
Question No : 253) During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship. Which of the following should the project manager receive from the team members? (Select two.)
A. Durations
B. Start/finish dates
C. Dependencies
D. Resources
E. Baseline
Question No : 254) A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, theproject manager submits a change request that contains which of the following?
A. Description, cost difference of the replacement, and WBS
B. Description, justification, and cost
C. Cost difference of the replacement, justification, and communications plan
D. Description, quality impact, and cost
Question No : 255) A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
A. Change validation with quality checks
B. Regression planning
C. Identify approval authority
D. Change implementation
PK0-005 Answers