Question No : 256) A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?
A. Crashing the schedule
B. Prioritizing tasks
C. Determining milestones
D. Developing sprints
Question No : 257) A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
A. Revise the project plan.
B. Update the issue log.
C. Request additional funding.
D. Issue a change request.

Question No : 258) A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
A. Risk identification
B. Gate review
C. Resource allocation
D. Resource leveling

Question No : 259) During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
A. risk identification

B. risk prioritization

C. risk qualification

D. risk quantification

Question No : 260) Resources for a project report to a project manager and a functional manager. The organizational structure is:
A. Matrix
B. Ad hoc
C. Functional
D. Projectized

Question No : 261) As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan. Which of the following documents should be reviewed FIRST to uncover the issue?
A. Communications plan
B. Scope statement
C. Project management plan
D. Organizational chart

Question No : 262) A resource is assigned to two projects with two scheduled tasks that complete at the sametime. This is known as:
A. shared resource contention
B. intraproject resource contention
C. interproject resource contention
D. dedicated resource contention

Question No : 263) A PM is reviewing bids from vendors and has a question. Which of the following documents should the PM use to obtain a response?
A. Project schedule
B. RFP
C. Quotation
D. RFI

Question No : 264) When closing a project, which of the following must be completed to allow team members to return to their designated departments?
A. Perform retrospective
B. Release resources
C. Obtain sign-off from the sponsor
D. Close contracts

Question No : 265) A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer (CEO) directs that all meetings be conducted via video conference to save costs and expedite communication. This scenario is an example of:
A. outsourcing.
B. corporate acquisition.
C. internal reorganization.
D. process change.
E. relocation.
F. resource management.

Question No : 266) During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?
A. The quality of the deliverable decreased due to the rising material cost.
B. The PM did not follow the project communication plan.
C. Quality assurance actions were not adjusted for the vendor change.
D. The change was not documented and approved.

Question No : 267)Which of the following represents additional unauthorized requirements from the client?
A. Scope creep
B. Changing scope baseline
C. Change request
D. Gold plating

Question No : 268) A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?
A. Schedule
B. Milestone
C. Gate
D. Task

Question No : 269) Despite receiving regular updates, a sponsor learns a project recently slipped. Which of the following documents can the sponsor review to determine the project’s performance? (Select two.)
A. Status report
B. Communication plan
C. Issue log
D. Project schedule
E. Action items list
F. Risk register
Question No : 270) Which of the following features describe a projectized organization? (Select two.)
A. The project manager has less authority over the project team than in a strong matrix.
B. Team members are solely dedicated to project activities.
C. The functional manager has full authority over the project team members.
D. The project manager has full authority over the project team members.
E. Team members from various departments are assigned to the project.

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.