CompTIA Project plus (+) {PK0-005} Free Questions - Part 21
Question No : 301) While developing a project schedule, the project manager is attempting to sequence the following tasks:
Which of the following is the correct sequence for the above tasks?
A. F, C, A, E, B, D
B. F, E, C, B, A, D
C. F, A, B, C, E, D
D. D, B, E, F, C, A
Question No : 302) Which of the following primary factors are used to prioritize the development of risk response strategies? (Choose two.)
A. Likelihood
B. Timeline
C. Impact
D. Quality
E. Cost
Question No : 303) Which of the following are the BEST risk analysis tools to determine a project’s risk level? (Select two.)
A. Fishbone diagram
B. RACI matrix
C. Monte Carlo
D. Process flowchart
E. Expert judgment
F. Project dashboard
Question No : 304) A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
? Project title description
? Preassigned resources
? Budget
? WBS
? Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
A. Project title and description
B. Preassigned resources
C. Budget
D. WBS
E. Measurable project objectives
Question No : 305) Which of the following risk strategies prevents a risk from impacting a project?
A. Accept risk
B. Mitigate risk
C. Avoid risk
D. Transfer risk
Question No : 306) A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take. Which of the following activities does this describe?
A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk qualification
Question No : 307) Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
A. Requirements
B. Lessons learned
C. Budget
D. Environment
Question No : 308) In which of the following situations is a project manager MOST likely to use a process diagram?
A. When describing a new business idea for the team to review
B. When describing a new business workflow for the team to implement
C. When describing a new business project for the team to implement
D. When describing a new business acquisition for the team to review
Question No : 309) A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?
A. Identifying the risk
B. Obtaining approval from the CCB
C. Evaluating the impact of the risk
D. Communicating to stakeholders
Question No : 310) A customer has stated that meeting the project schedule and milestones takes priority andis, therefore, willing to spend additional funds to sustain operations. The project team must ensure completion of the:
A. business continuity plan.
B. incident response plan.
C. disaster recovery plan.
D. risk management plan.
E. quality management plan.
Question No : 311) Which of the following documents ensures two parties do not share contractually binding information?
A. C&D letter
B. RFI
C. NDA
D. MOU
Question No : 312) Which of the following is a reason for assessing risk in a project?
A. To identify new tasks
B. To shorten the project timeline
C. To avoid rework
D. To establish a budget
Question No : 313)Which of the following provides tools and standard documentation for the project team?
A. Project management office
B. Project manager
C. Project coordinator
D. Project steering committee
Question No : 314) A project manager is required to maintain various documents and procedures. Which of the following require ongoing attention and periodic updates?
A. Project charter
B. Change requests
C. Project management plan
D. Communication plan
E. Project SOW
Question No : 315) A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?
A. Stakeholders
B. Scrum master
C. Project sponsor
D. Project team