Logo
  • Home
  • All Courses
    • Amazon - AWS
    • Cisco
    • CompTIA
    • EC Council
    • Microsoft
    • Oracle
    • Salesforce
    • Snowflake
  • Testimonials
  • Blogs
  • Login
  • Register
  • Cart

CompTIA Project plus (+) {PK0-005} Free Questions - Part 24

Question No : 346) A PM is asked to keep the Chief Information Officer (CIO) informed of a project’s health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information?
A. Status report
B. Meeting minutes
C. Dashboard
D. Email

Question No : 347) A diagram or chart is required to illustrate data differences given the following:
1. The diagram or chart must track at least two variables to determine the relationship
between independent variables and include a regression or trend line.
2. The diagram or chart should include cause effect analysis and investigate historical
information.
Which of the following should be used given these requirements?
A. Pareto Chart
B. Ishikawa Diagram
C. Histogram
D. Probability diagram
E. Run chart
F. Scatter chart
Question No : 348) A project manager is analyzing the cost variances produced when comparing two different projects completions. 

A project manager is analyzing the cost variances produced when comparing two different projects completions.

Which of the following factors could be causing the increased variance for the four-month projects? (Select two.)
A. Increased resource productivity
B. Increased resource allocation
C. Increased schedule variance
D. Increased labor cost
E. Increased labor overhead

Question No : 349) Which of the following documents are considered mutually binding? (Choose two.)
A. NDA
B. PO
C. RFP
D. WBS
E. KPI

Question No : 350) A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays. Which of the following is the BEST risk response strategy?
A. Exploit
B. Enhance
C. Mitigate
D. Communicate

Question No : 351) Which of the following statements are correct regarding project management? (Select two.)
A. A project can be part of an organization’s program management.
B. An organization’s portfolio will include programs.
C. A program has a defined start and finish.
D. An organization’s portfolio is a temporary and unique endeavor.
E. A project portfolio will be managed under program management.

Question No : 352) During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
A. Ask the team member to move to a different test environment.
B. Ask the team member to refrain from testing the scenarios.
C. Revisit the risk management plan and provide corrective actions.
D. Revisit the contingency plan and provide corrective actions.
Question No : 353) A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of
awareness of changes to the project schedule?
A. Define the communications plan.
B. Record the missed tasks on the issue log.
C. Provide meeting minutes after each call.
D. Complete a fishbone diagram.

Question No : 354) Which of the following are mutually binding project documents? (Select two.)
A. Quotation
B. Letter of intent
C. Proposal
D. Evaluation
E. Warranty
F. Charter

Question No : 355) A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?
A. Functional

B. Projectized

C. Strong matrix

D. Flat

Question No : 356) A project manager has been experiencing resistance from a group of stakeholders. With which of the following should the project manager consult to reduce friction going forward?
A. Project scheduler
B. Project coordinator
C. Project sponsor
D. Project management office

Question No : 357) The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:
A. Transference
B. Sharing
C. Avoidance
D. Acceptance

Question No : 358) A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
A. Have the team members deny all change requests from this stakeholder
B. Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
C. Contact the key stakeholder to encourage the submission of written change requests
D. Request additional resources from the project team to complete the change requests from the key stakeholder

Question No : 359) A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?
A. 0.3
B. 1.2
C. 2.0
D. 3.0

Question No : 360) In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?
A. The project is behind schedule
B. The project is over budget
C. The project has float available
D. The project needs a gate review
 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.