Question No : 361) Which of the following are mutually binding project documents? (Select two.)
A. Quotation
B. Letter of intent
C. Proposal
D. Evaluation
E. Warranty
F. Charter

Question No : 362) Which of the following techniques modifies the schedule based upon resource constraints?
A. Critical Chain Method
B. Critical Path Method
C. Arrow Diagramming Method
D. Precedence Diagramming Method

Question No : 363) A project schedule lists a resource as 50% because it likely:
A. is a shared resource.
B. depict a resource shortage.
C. signifies overallocation of a resource.
D. notes underallocation of a resource.
Question No : 364) Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?
A. SLA
B. Project charter
C. Risk register
D. RFP

Question No : 365) Which of the following resources outlines consequences of non-performance?
A. Project sponsor
B. Project team
C. Customer
D. Project management office

Question No : 366) The project manager needs to motivate the team; however, is an insufficient budget for awards. Which of the following motivating agents is the MOST appropriate option the project manager can utilize?
A. Reduce the workload

B. Replace resources

C. Extend the timeline

D. Provide additional responsibility

Question No : 367) A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk response

Question No : 368) Given the following sprint:

Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?

Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
A. Gantt chart

B. Pareto chart

C. Scatter chart

D. Burndown chart

Question No : 369) A project manager has developed the initial schedule for an upcoming project.

A project manager has developed the initial schedule for an upcoming project.

Using the attached schedule, which of the following is the critical path?
A. 12 days
B. 14 days
C. 16 days
D. 17 days

Question No : 370) Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members. Which of the following steps should the PM take to make the meetings more productive? (Select two.)
A. Facilitate the meetings by adhering to the agenda.
B. Encourage interaction among team members during the meetings.
C. Ensure meetings minutes are accurately recorded.
D. Adjust the number of meetings.E. Change the number of action items.
F. Schedule impromptu meetings when the SME is absent.

Question No : 371) A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial. This would likely impact the project’s: (Select two.)
A. environment
B. scheduling
C. requirements
D. quality
E. scope
F. budget

Question No : 372) A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?
A. Repetitive
B. Ongoing
C. Iterative
D. Temporary

Question No : 373) A team member has reported Task 3 will be completed ahead of schedule. 

A team member has reported Task 3 will be completed ahead of schedule.

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
A. 8 days
B. 10 days
C. 11 days
D. 12 days

Question No : 374) A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control was missed?
A. Communicate the change
B. Quality check
C. Implementation
D. Evaluate impact and justification

Question No : 375) Which of the following should a project manager consider as part of a make or buy analysis?
A. Organization type

B. KPIs

C. Project charter

D. Trade secrets
 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.