Question No : 376) The following tasks are required to complete an IT project that is behind schedule:
Which of the following is the critical path?
A. 3, 2, 4
B. 4, 2, 3
C. 3, 2, 1, 4
D. 4, 1, 2, 3
Question No : 377) Under an Agile methodology, standup meetings occur:
A. daily
B. twice daily
C. weekly
D. ad hoc
Question No : 378)Which of the following is the MOST important component against which the project manager can analyze project performance?
A. Burn rate
B. Project baselines
C. KPIs
D. Budget
Question No : 379) A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint described in this scenario is:
A. cost
B. environmental
C. scope
D. scheduling
Question No : 380) Which of the following captures unforeseen activities throughout the project that need attention and resolution?
A. Gantt chart
B. Action items
C. Project schedule
D. Meeting minutes
Question No : 381) A project manager procures additional resources from a local company. Which of the following-describes this event?
A. Reorganizing
B. Onboarding
C. Offshoring
D. Outsourcing
Question No : 382) Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
A. Managing change
B. Fast tracking
C. Rolling wave planning
D. Crashing
Question No : 383) A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
A. Individually call all project team members.
B. Send an email to all project team members.
C. Schedule a conference call.
D. Schedule a face-to-face meeting.
Question No : 384) The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project’s success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
A. Wiki page
B. Intranet
C. Extranet
D. Internet
E. Knowledge base
Question No : 385) A project has activities on the critical path that must be completed before other activities can start:
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
A. B, A, D
B. C, B, D, A
C. D, A, C
D. B, C, A, D
Question No : 386)Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
A. Email and instant messaging to project team members and the project team members and the project sponsor
B. Text messages to and voice conferences with all stakeholders and project team members
C. Video conferences with key stakeholders and the project champion
D. Instant messaging to the project coordinator and project scheduler
Question No : 387) Which of the following documents will provide the MOST detailed information regarding the work a vendor will perform during a project?
A. RFI
B. SLA
C. SOW
D. PO
Question No : 388) Based on the table below:
Which of the following is the total float for the critical path?
A. 0
B. 1
C. 2
D. 3
Question No : 389) A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
A. Go over the meetings objectives and agenda.
B. Brief the team on which tasks have fallen behind schedule and where the project has slack.
C. Refer to the risk register to map the risks to issues and mitigation strategies.
D. Review the issue log with the project team and identify potential risks.
E. Review an Ishikawa diagram with the project team to determine possible causes and effects.
Question No : 390) A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?
A. Norming
B. Performing
C. Forming
D. Storming