CompTIA Project plus (+) {PK0-005} Free Questions - Part 26

Question No : 376) The following tasks are required to complete an IT project that is behind schedule: 

The following tasks are required to complete an IT project that is behind schedule

Which of the following is the critical path?
A. 3, 2, 4
B. 4, 2, 3
C. 3, 2, 1, 4
D. 4, 1, 2, 3

Question No : 377) Under an Agile methodology, standup meetings occur:
A. daily
B. twice daily
C. weekly
D. ad hoc

Question No : 378)Which of the following is the MOST important component against which the project manager can analyze project performance?
A. Burn rate
B. Project baselines
C. KPIs
D. Budget

Question No : 379) A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint described in this scenario is:
A. cost
B. environmental
C. scope
D. scheduling

Question No : 380) Which of the following captures unforeseen activities throughout the project that need attention and resolution?
A. Gantt chart
B. Action items
C. Project schedule
D. Meeting minutes
Question No : 381) A project manager procures additional resources from a local company. Which of the following-describes this event?
A. Reorganizing
B. Onboarding
C. Offshoring
D. Outsourcing

Question No : 382) Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
A. Managing change
B. Fast tracking
C. Rolling wave planning
D. Crashing

Question No : 383) A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
A. Individually call all project team members.
B. Send an email to all project team members.
C. Schedule a conference call.
D. Schedule a face-to-face meeting.
Question No : 384) The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project’s success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
A. Wiki page
B. Intranet
C. Extranet
D. Internet
E. Knowledge base

Question No : 385) A project has activities on the critical path that must be completed before other activities can start:
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
A. B, A, D
B. C, B, D, A
C. D, A, C
D. B, C, A, D

Question No : 386)Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
A. Email and instant messaging to project team members and the project team members and the project sponsor
B. Text messages to and voice conferences with all stakeholders and project team members
C. Video conferences with key stakeholders and the project champion
D. Instant messaging to the project coordinator and project scheduler

Question No : 387) Which of the following documents will provide the MOST detailed information regarding the work a vendor will perform during a project?
A. RFI
B. SLA
C. SOW
D. PO

Question No : 388) Based on the table below:

Which of the following is the total float for the critical path?

Which of the following is the total float for the critical path?
A. 0
B. 1
C. 2
D. 3

Question No : 389) A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
A. Go over the meetings objectives and agenda.
B. Brief the team on which tasks have fallen behind schedule and where the project has slack.
C. Refer to the risk register to map the risks to issues and mitigation strategies.
D. Review the issue log with the project team and identify potential risks.
E. Review an Ishikawa diagram with the project team to determine possible causes and effects.

Question No : 390) A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?
A. Norming
B. Performing
C. Forming
D. Storming

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 29-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.