CompTIA Project plus (+) {PK0-005} Free Questions - Part 28
Question No : 406) A small company has a successful proof of concept for an innovative new service but lacks the necessary expertise to deploy it. Which of the following is the BEST course of action to address this deficiency?
A. Internal reorganization
B. Business merger/acquisition
C. Business process change
D. Outsourcing
Question No : 407) Input into a project’s requirements is needed for clarification. With which of the following roles would the project manager MOST likely consult?
A. Project risk manager
B. Project stakeholder
C. Project scheduler
D. Project coordinator
Question No : 408)The quarterly financial statement has been released, and portfolios are losing funding for projects. Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)
A. Shorten the project duration.
B. Reduce the features being released.
C. Request more time with a smaller project team.
D. Reduce quality control.
E. Ask for operational team support.
Question No : 409) Which of the following is the BEST indicator of project failure?
A. Product deficiencies revealed during the monitor and control phase
B. Project team members disagreeing on milestones
C. Project deliverables completed behind schedule
D. Several changes being made to the project
Question No : 410) A company’s Chief Executive Officer (CEO) has asked the project manager to update upper management regarding the status of a project. The project manager sends weekly written reports to the CEO and upper management. The project manager receives feedback that several administrators are frustrated with the level of detail and the frequency of the updates. Which of the following is the BEST step for the project manager to take to resolve this issue?
A. Customize the reports for each administrator in their preferred manner.
B. Set up a meeting with the supervisor to discuss and resolve the issue.
C. Stop sending reports and wait for upper management to talk to the project manager about their preferences.
D. Start giving verbal reports to upper management so they can hear about the project in person.
Question No : 411) In a highway construction project, the project team has identified the need to utilize additional land for staging equipment. After documenting the change request, which of the following should be accomplished NEXT?
A. Communicate with the stakeholders
B. Audit the documentation
C. Obtain approval
D. Identify the approval authority
Question No : 412) An external consultant reviews benchmark staffing for an organization every three years. Which of the following is MOST likely occurring?
A. Acquisition
B. Relocation
C. Reorganization
D. Merger
Question No : 413) During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium. Which of the following is the BEST course of action?
A. Increase the contingency reserve.
B. Add the risks to the watch list.
C. Establish and monitor trigger conditions.
D. Assign the sponsor as the primary risk owner.
Question No : 414) A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:
A. dedicated resources.
B. interproject dependencies.
C. resource overallocation.
D. shared resources.
Question No : 415) Which of the following roles is MOST involved in checking the quality of the deliverables and supporting the project manager during the project?
A. Sponsor
B. Team leader
C. Project coordinator
D. Tester
Question No : 416) The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?
A. Identify task relationships.
B. Put the resources on tasks.
C. Set the quality gates.
D. Estimate the work package.
Question No : 417) Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)
A. Business continuity response
B. Milestone achievement
C. Incident response
D. Schedule change
E. Change request
F. Stakeholder changes
Question No : 418) Which of the following indicators would help the project manager to determine the financial status of the project?
A. CV
B. SV
C. EV
D. PV
E. COQ
F. AC
G. BAC
Question No : 419)A new project manager is assigned in the middle of a seven-month project. The project is behind schedule, and there is only historical weekly cost data available. Which of the following best practices should the project manager perform to assess project costs?
A. Review the SPI.
B. Create a burndown chart.
C. Ask the project sponsor for additional funding.
D. Perform a cost benefit analysis.
Question No : 420) Which of the following is performed during the monitoring and controlling phase?
A. Quality control and training plan development
B. Creation of schedule and fund deliverables
C. Development of transition plan and finalizing contracts
D. Quality assurance and governance oversight
PK0-005 Answers