Logo
  • Home
  • All Courses
    • Amazon - AWS
    • Cisco
    • CompTIA
    • EC Council
    • Microsoft
    • Oracle
    • Salesforce
    • Snowflake
  • Testimonials
  • Blogs
  • Login
  • Register
  • Cart

CompTIA Project plus (+) {PK0-005} Free Questions - Part 29

Question No : 421) Which of the following documents is a snapshot in time of a project during the execution phase?
A. Scope document
B. Performance indicators
C. Status report
D. Risk register

Question No : 422) Two highly skilled resources, who are currently working on other projects, are assigned to a project manager. Personality conflicts between the two resources have adversely affectedproject completion. The project manager has asked a manager with direct authority over the resources to provide input to resolve the issue, but the project manager does not have the level of authority required to resolve the personality conflict. Which of the following structure types is this an example of?
A. Strong matrix
B. Balanced matrix
C. Functional
D. Weak matrix
E. Projectized

Question No : 423) A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?
A. There were not enough resources assigned to the project execution team.
B. The PMO was not involved in project initiation and planning.
C. Proper team-building activities were not performed when starting the project.
D. A few major stakeholders were overlooked during project initiation and planning.

Question No : 424) A project manager failed to include quality testing in a software development project plan and must now add it while the project is underway. Which of the following BEST describes the relationship that quality will have on the triple constraint?
A. Time, cost, and scope will decrease.

B. Time and scope will remain static, and costs will increase.

C. Time and cost will increase, and scope will remain constant.

D. Time will remain static, and scope and costs will increase.

Question No : 425) A project manager wishes to track a project’s performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?
A. Determine the critical path.
B. Determine the milestones.
C. Set phase gates
D. Set a baseline.

Question No : 426) Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?
A. The cost will increase.
B. There will be no impact.
C. The scope will change.
D. The schedule will change.

Question No : 427) A solid line is connecting a project team member to two people above the member on the organizational chart. Which of the following types of organization does this indicate?
A. Functional

B. Merged

C. Split

D. Matrix

Question No : 428) A senior developer abruptly resigned without notice. Because of the senior developer’s expertise, the active task workload was substantial. This would MOST likely impact the project’s: (Choose two.)
A. environment
B. scheduling
C. requirements
D. effectiveness
E. scope
F. budget

Question No : 429) Which of the following are characteristics of a matrix organization? (Choose three.)
A. The project manager has full authority.
B. Resources report directly to the functional manager.
C. Authority is shared between functional and project managers.
D. Resources are assigned from functional area to project.
E. There is ad hoc resourcing.
F. The organization utilizes a bench.
G. The project manager authority ranges from strong to weak.

Question No : 430)Which of the following is the BEST reason to conduct regular risk reviews?
A. Risk reviews ensure stakeholders take action on assigned items.
B. Risk reviews allow for the identification of response strategies.
C. Risk reviews can keep personnel on track with their assigned tasks.
D. Risk reviews must be reported in status updates.

Question No : 431) Which of the following should be used to identify where slack is occurring in the project schedule and determine the critical path?(Choose two.)
A. PERT chart
B. Risk register
C. Arrow diagram method
D. RACI matrix
E. Project charter
F. Fishbone diagram

Question No : 432) After accepting and assigning a positive risk, risk owners have a responsibility to:
A. maximize the probability.
B. update the risk register.
C. minimize the impact.
D. determine a mitigation strategy.

Question No : 433) Which of the following is the first document issued during the procurement process in a project?

A. PO
B. RFP
C. RFI
D. RFQ

Question No : 434) A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
A. SLA
B. SOW
C. LOI
D. RFQ

Question No : 435) A key team member found a new job and will be leaving in two weeks. Which of the following should the project manager do FIRST to minimize negative impacts to the project?
A. Request a replacement from the project sponsor.
B. Contact human resources to initiate the termination process.
C. Involve the legal department for contract review.
D. Inform executive management about attrition.

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.