Question No : 451) For most organizations, which of the following is the MOST efficient method to communicate the project status to a large group of stakeholders?
A. Email messages
B. Internet site
C. Conference calls
D. Instant messages

Question No : 452) Given the table below for a house construction project:

Given the table below for a house construction project:

The table above is an example of which of the following project artifacts?
A. Project plan
B. SOW
C. WBS
D. RTM
E. RBS
F. Status report

Question No : 453) Which of the following should receive regular communication during the planning phase of a project? (Choose two.)
A. Collaboration site
B. Change control board
C. Subject matter experts
D. Sponsor
E. Human resources

Question No : 454) A project manager, who previously worked at a construction firm, has just joined an IT organization and has been assigned to handle a security project. Which of the following roles can provide technical direction during the course of the project?
A. Security SME
B. Business analyst
C. Project scheduler
D. Project sponsor

Question No : 455) Which of the following should be updated FIRST, once the hurricane season has ended?
A. Scope statement
B. Issue log
C. Risk register
D. Communications plan
Question No : 456) A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
A. Immediately send the current weekly status report
B. Add email to the distribution list for the weekly status report
C. Remove email from the distribution list for the monthly status report
D. Consult the communications plan and act accordingly

Question No : 457) A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the project domain to be:
A. delegated
B. instructed
C. consulted
D. employed

Question No : 458) A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time. Which of the following is the BEST option for the project to complete on time and within parameters?
A. Reduce the project scope.
B. Crash the schedule.
C. Request additional budget from the customer.
D. Apply new resources to the project.
Question No : 459) Two parties are beginning conversations regarding the purchase of professional services. Which of the following should be in place FIRST?
A. RFP
B. SOW
C. NDA
D. LOI

Question No : 460) Adhering to the project budget is MOST important during which of the following project phases?
A. Planning
B. Initiating
C. Monitor and controlling
D. Closing

Question No : 461) A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)
A. Milestones
B. Stakeholder changes
C. Audits
D. Schedule changes
E. Incident response
F. Business continuity response
G. Risk register updates

Question No : 462) A project requires the distribution of training materials for 300 stakeholders across multiple campuses. Which of the following would be the BEST method to deliver the materials?
A. Email
B. Printed media
C. Face-to-face meetings
D. Video conferencing

Question No : 463) Which of the following is the BEST technique for comparing actual or planned project practices to those of comparable projects?
A. Benchmarking
B. Pareto chart
C. Histogram
D. Fishbone diagram

Question No : 464) A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
A. an internal reorganization.

B. outsourcing.

C. a business process change.

D. resource allocation.

Question No : 465) A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast. Which of the following would BEST avoid the risk of rain damage?
A. Place a tarp over the fresh concrete to protect it.
B. Refinish the concrete if it rains during that time.
C. Pour the concrete as quickly as possible to allow the most drying time.
D. Wait to pour the concrete until rain is not in the forecast.

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.