Question No : 481) Risk ID 2 has occurred. 

Risk ID 2 has occurred.

Which of the following ways should the project manager update the risk register?
A. Add a column for probability and set risk 2 at 100%
B. Change the risk 2 response to backups restored
C. Change the risk 2 status to issue
D. Change the risk 2 owner to PM

Question No : 482) Company A recently partnered with Company B. Over the past few months, multiple teams have been working to refine internal processes to deliver products in a more timely manner. If the effort is successful, which of the following will MOST likely occur?
A. Reorganization
B. Relocation
C. Outsourcing
D. Demerger

Question No : 483) A project sponsor decides to cut the project budget and reduce the scope. As a mitigation plan, the team decides to promote the project internally to gain support from other areas. Which of the following describes the BEST combination of communication methods that can be used to attract more people?
A. Gate reviews, face-to-face meetings, and kickoff meeting

B. Social media, email, and printed media

C. Instant messaging, kickoff meeting, and town hall meetings

D. Text messaging, instant messaging, and meetings

Question No : 484) A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?
A. Update the issue log.
B. Update the risk register.
C. Conduct a risk review meeting.
D. Submit a change request to address the risk.

Question No : 485) Rather than sending emails to communicate all project information, the project manager:
? Makes telephone calls to key stakeholders for urgent information
? Sends emails for routine information
? Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?
A. Prioritizing based on personal preferences
B. Tailoring the method based on message content
C. Adjusting the method based on confidentiality constraints
D. Demonstrating concern for technological factors

Question No : 486) A project manager detects a defect in a project deliverable and suspects a team member missed a step during production.Which of the following tools would be BEST for the project manager to use to confirm this suspicion?
A. Pareto chart
B. Process diagram
C. Run chart
D. Fishbone diagram

Question No : 487) A cost baseline is used to measure the:
A. eventual cost of a project.
B. increase in the budget.
C. variance with the initial budget.
D. inevitable cost overruns.

Question No : 488) A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise. Which of the following contains actions the team is MOST likely to consider?
A. Identify, collaborate, quantify
B. Accept, mitigate, transfer
C. Stop, review, plan
D. Prioritize, qualify, engage
Question No : 489) Detailed policy guidance is BEST provided by:
A. an intranet site
B. a text message
C. a video conference
D. an email

Question No : 490) A project manager needs a systems administrator as a resource on a project. The project manager approaches the operations manager to obtain the resource. In which of the following organizational structures is the project manager MOST likely operating?
A. Hybrid
B. Projectized
C. Functional
D. Matrix

Question No : 491) The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project.

The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project.

Which of the following changes would BEST satisfy the project sponsor?
A. Add the project sponsor to all project email correspondence moving forward
B. Include the project sponsor in all project meetings moving forward
C. Add a new line to the communications plan to provide a weekly status report with a dashboard
D. Include the project sponsor in the daily stand-up with the entire project team

Question No : 492) The PMO is coordinating a series of interrelated functions to achieve a specific business goal. These functions require non-unique operational processes. Which of the following is the PMO organizing?
A. Network diagram
B. Product backlog
C. Program
D. Portfolio

Question No : 493) Which of the following is primarily responsible for developing the timeline?
A. Project sponsor
B. Project coordinator
C. Project manager
D. Project scheduler
Question No : 494) Which of the following is the BEST source for identifying the defect tolerance of a project?
A. SOW
B. SWOT
C. KPP
D. SLA

Question No : 495) A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?
A. Projectized
B. Functional
C. Flat
D. Strong matrix
 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.