Question No : 496) A project sponsor wants to know which tasks are next in the project but is unable to find this information. Which of the following may need to be adjusted?
A. Scope document
B. Status report
C. Issue log
D. Risk log
Question No : 497) To maintain an active project’s progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?
A. Mitigating
B. Negotiating
C. Forcing
D. Avoiding
E. Accepting
Question No : 498) Which of the following activities is MOST likely to be completed in the closing project phase?
A. Operational training
B. Testing deliverables
C. Updating the scope statement
D. Performing a final quality check
Question No : 499) Which of the following project team members would MOST likely be tasked with maintaining project documents?
A. Project coordinator
B. Project manager
C. Project scheduler
D. Project sponsor
E. Project champion
Question No : 500) Objectives and tasks are equally assigned by two different managers. Which of the following BEST describes this organization type?
A. RACI
B. Functional
C. Matrix
D. Projectized
Question No : 501) Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)
A. Warranty
B. SLA
C. Purchase order
D. Letter of intent
E. RFQ
F. IMS
Question No : 502) A testing event was held and deemed unsuccessful. After review, it becomes clear that the two project teams had different expectations of the testing. Which of the following is needed between the two teams?
A. Communication plan
B. Project schedule
C. Status report
D. Use case
Question No : 503) On larger projects, a vendor may occasionally proceed upon receipt of the:
A. ROE.
B. RFI.
C. NDA.
D. LOI.
Question No : 504) A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?
A. Risk identification
B. Gate review
C. Resource allocation
D. Resource leveling
Question No : 505) Which of the following BEST describes the relationship between portfolios, projects, and programs?
A. A group of programs makes up a project, and all of an organization's projects make up a portfolio.
B. A group of projects makes up a program, and all of an organization's programs make up a portfolio.
C. A group of portfolios makes up a program, and all of an organization's programs make up a project.
D. A group of projects makes up a portfolio, and all of an organization's portfolios make up a program.
Question No : 506) Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project. Which of the following describes the information the new ticketing system would provide?
A. RTM
B. KPIs
C. BAC
D. ETC
Question No : 507) A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
A. business change response
B. change management response
C. business continuity response
D. risk management response
Question No : 508) A project manager is collecting the number of hours, the resources, and the amount ofmoney spent on hardware and software. Which of the following is MOST likely the purpose of collecting this information?
A. Financial stability
B. Competitive advantage
C. Budget constraints
D. Expenditure tracking
Question No : 509) Which of the following normally would be completed prior to a vendor responding to an RFP?
A. PO
B. Contract
C. SLA
D. NDA
Question No : 510) Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)
A. Qualitative assessments are more difficult.
B. Qualitative assessments are faster.
C. Qualitative assessments require fewer resources.
D. Qualitative assessments provide more accurate results.
E. Qualitative assessments better identify opportunities.