Question No : 541) A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:
A. project charter.
B. statement of work.
C. project plan.
D. project request.

Question No : 542) Which of the following characteristics would stakeholders MOST likely have?

A. Provide input, vested interest, affected by project
B. No vested interest, funding control, expertise
C. Project steering, funding control, vested interest
D. Expertise, provide input, good at controlling

Question No : 543) A busy project manager has a diverse set of stakeholders and team members with respect to age and cultural background. Which of the following is the BEST method for communicating to the project manager’s audiences?
A. Speak with each individual, and communicate with that individual according to stated and demonstrated preferences
B. Utilize a variety of communication methods, such as email, IM, conference calls, and face-to-face meetings, to reach all the audiences
C. Develop a communications plan that considers the individual’s impact on the project and preferred communication method
D. Determine a single best communication method to provide efficient and consistent communications to all the audiences

Question No : 544) A project has been created, and the project team has been identified. Which of the following is the NEXT step?
A. Release an article on the company blog.
B. Conduct a company town hall.
C. Host a kickoff meeting.
D. Post a notice on social media.

Question No : 545) Which of the following is a risk strategy?

A. Risk quantification
B. Risk avoidance
C. Risk identification
D. Risk review

Question No : 546) A manager is reviewing some projects with two project managers who are working on the financial system. Which of the following BEST describes this type of review?
A. Operations
B. Project
C. Portfolio
D. Program

Question No : 547) A project sponsor no longer wants to receive email communications and insists on physical paper copies. Which of the following BEST describes this situation?
A. Cultural differences
B. Personal preferences
C. Intraorganizational differences
D. Technological factors

Question No : 548) The stakeholders who are available for the user acceptance test do not understand the project’s requirements. The tester is trying to identify who requested the feature, but there is no information available. Which of the following components is missing?

A. RTM
B. Quality plan
C. Project schedule
D. SOW

Question No : 549) Top-level managers are considering joining certain projects, programs, and operations to be managed as a group. Which of the following is being considered?
A. Organizational changes
B. PMO establishments
C. Project interdependencies
D. Program development

Question No : 550) A project is moving into the next phase, and those involved with planning will not actually perform the work. After the project team members have been identified and assigned to do the work, which of the following has changed?
A. Project
B. Schedule
C. Baseline
D. Stakeholder

Question No : 551) Which of the following is the BEST reason to use a burndown chart?
A. To determine how much risk is still associated with the project
B. To predict when project work will be completed
C. To establish a backlog for project deliverables
D. To create a project charter

Question No : 552) A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:
A. outsourcing.
B. low-quality resources.
C. benched candidates.
D. resource planning.

Question No : 553) Which of the following methods should a project manager use to improve email communication for a time- sensitive, high-visibility global project? (Choose two.)
A. Limit email recipients to only required team members.
B. Increase the number of emails to encourage team interaction.
C. Set up emails with bold text and all caps in the subject line.
D. Eliminate acronyms from the email to avoid miscommunication.
E. Include more information to increase the length of each email message.
F. Include detailed technical consideration in each email.

Question No : 554) A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up tothe meeting. Which of the following MOST likely describes why this occurring?
A. There is no rapport between the team members and the project manager.
B. The time zone in the one country is outside of working hours.
C. The meeting is occurring too frequently.
D. Language barriers prevent team members from participating.

Question No : 555) A project manager is overseeing an outsourced team of contractors and subcontractors. One month into the project, the project manager realizes tasks are not being completed on time. Subcontractors are not available at the right time. Which of the following is the NEXT step for the project manager to take to get the project back on track?
A. Reevaluate which areas of the project need to be completed before other steps on the project are completed.
B. Hire a new contractor who can better handle the team of subcontractors.
C. Conduct training with the contractors and subcontractors so they can be more organized in their jobs.
D. Have a meeting with management for approval to reevaluate how the project could be run more smoothly.

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.