CompTIA Project plus (+) {PK0-005} Free Questions - Part 37
Question No : 541) A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:
A. project charter.
B. statement of work.
C. project plan.
D. project request.
Question No : 542) Which of the following characteristics would stakeholders MOST likely have?
A. Provide input, vested interest, affected by project
B. No vested interest, funding control, expertise
C. Project steering, funding control, vested interest
D. Expertise, provide input, good at controlling
Question No : 543) A busy project manager has a diverse set of stakeholders and team members with respect to age and cultural background. Which of the following is the BEST method for communicating to the project manager’s audiences?
A. Speak with each individual, and communicate with that individual according to stated and demonstrated preferences
B. Utilize a variety of communication methods, such as email, IM, conference calls, and face-to-face meetings, to reach all the audiences
C. Develop a communications plan that considers the individual’s impact on the project and preferred communication method
D. Determine a single best communication method to provide efficient and consistent communications to all the audiences
Question No : 544) A project has been created, and the project team has been identified. Which of the following is the NEXT step?
A. Release an article on the company blog.
B. Conduct a company town hall.
C. Host a kickoff meeting.
D. Post a notice on social media.
Question No : 545) Which of the following is a risk strategy?
A. Risk quantification
B. Risk avoidance
C. Risk identification
D. Risk review
Question No : 546) A manager is reviewing some projects with two project managers who are working on the financial system. Which of the following BEST describes this type of review?
A. Operations
B. Project
C. Portfolio
D. Program
Question No : 547) A project sponsor no longer wants to receive email communications and insists on physical paper copies. Which of the following BEST describes this situation?
A. Cultural differences
B. Personal preferences
C. Intraorganizational differences
D. Technological factors
Question No : 548) The stakeholders who are available for the user acceptance test do not understand the project’s requirements. The tester is trying to identify who requested the feature, but there is no information available. Which of the following components is missing?
A. RTM
B. Quality plan
C. Project schedule
D. SOW
Question No : 549) Top-level managers are considering joining certain projects, programs, and operations to be managed as a group. Which of the following is being considered?
A. Organizational changes
B. PMO establishments
C. Project interdependencies
D. Program development
Question No : 550) A project is moving into the next phase, and those involved with planning will not actually perform the work. After the project team members have been identified and assigned to do the work, which of the following has changed?
A. Project
B. Schedule
C. Baseline
D. Stakeholder
Question No : 551) Which of the following is the BEST reason to use a burndown chart?
A. To determine how much risk is still associated with the project
B. To predict when project work will be completed
C. To establish a backlog for project deliverables
D. To create a project charter
Question No : 552) A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:
A. outsourcing.
B. low-quality resources.
C. benched candidates.
D. resource planning.
Question No : 553) Which of the following methods should a project manager use to improve email communication for a time- sensitive, high-visibility global project? (Choose two.)
A. Limit email recipients to only required team members.
B. Increase the number of emails to encourage team interaction.
C. Set up emails with bold text and all caps in the subject line.
D. Eliminate acronyms from the email to avoid miscommunication.
E. Include more information to increase the length of each email message.
F. Include detailed technical consideration in each email.
Question No : 554) A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up tothe meeting. Which of the following MOST likely describes why this occurring?
A. There is no rapport between the team members and the project manager.
B. The time zone in the one country is outside of working hours.
C. The meeting is occurring too frequently.
D. Language barriers prevent team members from participating.
Question No : 555) A project manager is overseeing an outsourced team of contractors and subcontractors. One month into the project, the project manager realizes tasks are not being completed on time. Subcontractors are not available at the right time. Which of the following is the NEXT step for the project manager to take to get the project back on track?
A. Reevaluate which areas of the project need to be completed before other steps on the project are completed.
B. Hire a new contractor who can better handle the team of subcontractors.
C. Conduct training with the contractors and subcontractors so they can be more organized in their jobs.
D. Have a meeting with management for approval to reevaluate how the project could be run more smoothly.