CompTIA Project plus (+) {PK0-005} Free Questions - Part 40
Question No : 586) An audit, project change, task initiation/completion, gate review, and incident response are examples of:
A. change control.
B. status reporting.
C. risk events.
D. communication triggers.
Question No : 587) A project team is executing a transition plan for a project. During which of the following project phases does this normally occur?
A. Execution
B. Monitor and control
C. Closing
D. Planning
E. Initiation
Question No : 588) A company has been trying to implement a product with multiple challenges for more than two years. Both the company and the vendor mutually agree to cancel the project. Which of the following should be issued?
A. MOU
B. LOI
C. NDA
D. C&D
Question No : 589) A hurricane occurs in an area where several key project resources are located. Whenreviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?
A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget
Question No : 590) A vendor developed a new payroll system for a local transit authority. Due to the system’s complexity, the vendor will need to work with the transit authority for three months after system implementation. This will be documented in the:
A. warranty.
B. training plan.
C. WBS.
D. SLA.
Question No : 591) Which of the following metrics are used to determine a project's EAC?
A. Baseline costs plus actual costs
B. Forecasted costs plus actual costs
C. Planned costs minus actual costs
D. Forecasted costs minus actual costs
Question No : 592)A highly skilled project engineer will be on indefinite medical leave. No one on the project team has the required skill set to replace the engineer. Which of the following will be impacted MOST by the absence of the engineer?
A. Resources
B. Environment
C. Deliverables
D. Requirements
Question No : 593) Which of the following is the project phase when quality assurance occurs?
A. Planning
B. Closing
C. Execution
D. Scoping
E. Initiation
Question No : 594) An external customer has requested a modification of the project scope through an official change request. Which of the following is the appropriate NEXT step?
A. Implement the change.
B. Analyze impacts to the project.
C. Create a new change request.
D. Modify the configuration documentation.
Question No : 595)A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources. This is an example of:
A. a business process change
B. personal preference
C. internal reorganization
D. intraorganizational differences
Question No : 596) A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the QUESTION NO:?
A. Project schedule
B. Project management plan
C. Project charter
D. Staffing matrix
Question No : 597) A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date. Which of the following should the project manager do NEXT?
A. Ask the functional manager to release the 20% of allocation from the secondary project.
B. Ask the sponsor to negotiate with the project manager from the secondary project.
C. Ask the PMO to assign additional resources.
D. Ask the project manager of the secondary project to release the resource.
Question No : 598) During a meeting, a new member of the PMO says, “If this project fails, then the portfolio fails, and the program as a whole ultimately fails.” Which of the following errors is the new PMO member making?
A. The new PMO member has not review the intra organizational strategy.
B. The new PMO member does not realize that although a project can fail, a program cannot, as it contains all projects in a company.
C. The new PMO member has confused the relationship between portfolio and program.
D. The new PMO member has not had an opportunity to review the company’s project list.
Question No : 599) A project team has just implemented an approved change to a project. Which of the following should occur NEXT?
A. Validate the change.
B. Evaluate the impact of the change.
C. Implement a regression plan.
D. Update the issue log.
Question No : 600) Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?
A. Resources
B. Requirements
C. Scope
D. Funding
PK0-005 Answers