CompTIA Project plus (+) {PK0-005} Free Questions - Part 42

Question No : 616) As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?
A. Critical path
B. Milestone
C. Phase gate
D. Quality gate
E. Toll gate

Question No : 617) Which of the following documents would a project manager utilize to find a vendor for an undefined project?
A. RFP
B. RFI
C. RFQ
D. SOW
Question No : 618) A project team member informs the project manager that a task on the critical path will not be completed on time. Which of the following documents will MOST likely be updated? (Choose two.)
A. Project scope
B. Project charter
C. Project schedule
D. Risk register
E. Incident response plan
F. Communication plan

Question No : 619) A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
A. Regression plan
B. Quality plan
C. Change validation
D. Application version control

Question No : 620) A project manager needs to determine resource availability to assign the resources to project tasks. Which of the following will the project manager MOST likely use?
A. Resource calendars
B. Project calendar
C. Staffing management plan
D. Conflict resolution

Question No : 621) Which of the following project management roles is responsible for estimating the duration of tasks?
A. Project scheduler
B. Project team
C. Project manager
D. Project coordinator

Question No : 622) A project manager is not going to finish a project on time but cannot change the deadline or add more budget. Which of the following types of change would allow the project manager to finish the project successfully?
A. Resources
B. Communication
C. Organization
D. Quality

Question No : 623) Midway through a project, the building the team works in is destroyed by a hurricane. Which of the followingtypes of communication is BEST in this event?
A. Incident response
B. Business continuity response
C. Resource change response
D. Schedule response

Question No : 624) A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project. Which of the following has MOST likely occurred?
A. Scope creep
B. Gold plating
C. Task reprioritization
D. Lack of requirements

Question No : 625) A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder’s expectations?
A. Analyze the RASI chart
B. Review previous meeting minutes.
C. Initiate a change control request.
D. Updates the communications plan.
Question No : 626) A PM has a complex project that requires coordination among numerous stakeholders. Which of the following is the MOST appropriate type of meeting for the stakeholders to hold?
A. Virtual
B. Impromptu
C. One-on-one
D. In-person

Question No : 627) A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention. 

A project manager is developing a risk management plan and has decided to score each risk

Which of the following risks should the project manager accept? (Choose two.)
A. 1
B. 2
C. 3
D. 4
E. 5
F. 6

Question No : 628) Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?
A. Histogram, forecasting
B. Ishikawa, quality control
C. Scatter, determining resources
D. Gantt, leveraging resources

Question No : 629) A first-time project manager is developing a project charter. Which of the following are key elements to have the project charter approved? (Choose two.)
A. Project team
B. Business case
C. Detailed risks
D. Requirements
E. Service-level agreement
F. Detailed budget

Question No : 630) A project manager is managing an eight-month effort and has to report on the financial health once a month. No changes to the project will be approved going forward. Given the following table:

The project’s burn rate is also decreasing by 10% monthly over the remainder of time. Which of the following BEST describes the project’s financial health?
A. The project will burn $36,585, resulting in a net deficit of $11,585
B. The project will burn $54,615, resulting in a net deficit of $29,615
C. The project will burn $40,500, resulting in a net deficit of $15,500
D. The project will burn $45,000, resulting in a net deficit of $20,000

 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 08-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.