Question No : 661) A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
A. Provide the next task to the newly freed resource.
B. Communicate the success to the team.
C. Notify the project sponsor of the new completion date.
D. Update the schedule and add lag to the next task.
Question No : 662) Which of the following is a suitable situation in which to apply the Agile methodology?
A. A very well-defined RFP
B. A fixed price contract
C. High-level requirements
D. Clear goals and large teams
Question No : 663) A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.
Which of the following is the NEXT appropriate step for the project manager to take?
A. Identify risk strategies for the realized events
B. Change the risk status to closed for 2 and 6
C. Consult the risk management plan
D. Update the issue log
Question No : 664) A project manager receives an initial project assignment. Which of the following documents is MOST likely to indicate the organizational structure for the project?
A. Communication management plan
B. Baseline
C. Business case
D. Organizational breakdown structure
Question No : 665)The vendor management team has requested all project managers to provide proof to back up complaints on vendor resolution delays. Which of the following will provide this information?
A. Scope statement
B. Project plan
C. Action items
D. Issue log
Question No : 666) Given the following:
Which of the following is the duration of the critical path?
A. 35 days
B. 37 days
C. 38 days
D. 72 days
E. 73 days
Question No : 667) A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional insurance. Which of the following risk responses has occurred?
A. Avoiding
B. Mitigating
C. Accepting
D. Transferring
Question No : 668) A project’s stakeholders have not been informed of project updates and milestones by the CCB and project team. The stakeholders have threatened to withdraw project support. Which of the following should the project manager do to get buy-in from the stakeholders for the project?
A. Update the communications plan to include the stakeholders
B. Expedite completion of the project before support is withdrawn by the stakeholders
C. Revise the quality management plan to include the project stakeholders
D. Increase the number of status reports provided to the project stakeholders
Question No : 669) Which of the following documents will MOST likely result in a time and material agreement?
A. RFQ
B. RFI
C. SLA
D. RFB
Question No : 670) A project team is creating a new product, and stakeholders are having a hard time understanding the product. Which of the following should be sent to the stakeholders?
A. Printed sketches and potential uses
B. Memo outlining high-level requirements
C. Sponsor mandate for the product
D. Link to the project's intranet site to review status reports
Question No : 671) During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training. Which of the following communication methods should be used?
A. Project communications plan
B. Project dashboard
C. Project schedule
D. Project status report
Question No : 672) Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.Which of the following steps should the project manager take NEXT?
A. Supply Ann with the requested tablet.
B. Have Ann submit a change request.
C. Provide Ann with a copy of the project management plan.
D. Inform Ann that she will receive what has been authorized.
Question No : 673) Which of the following project team members is responsible for managing quality assurance?
A. Project stakeholder
B. Project sponsor
C. Project manager
D. Project scheduler
Question No : 674) The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT?
A. Announce the fast track to the project team.
B. Modify the schedule
C. Initiate a change request.
D. Obtain approval.
Question No : 675)A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization. Which of the following BEST describes the constraints involved?
A. Deliverables, schedule, and resources
B. Stakeholders, scope, and schedule
C. Schedule, quality, and deliverables
D. Resources, requirements, and scope