Logo
  • Home
  • All Courses
    • Amazon - AWS
    • Cisco
    • CompTIA
    • EC Council
    • Microsoft
    • Oracle
    • Salesforce
    • Snowflake
  • Testimonials
  • Blogs
  • Login
  • Register
  • Cart

CompTIA Project plus (+) {PK0-005} Free Questions - Part 27

Question No : 391) A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
A. project management plan
B. scope statements and issue log
C. project dashboard and status report
D. action items and meeting minutes

Question No : 392) Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
A. Steer the project
B. Provide governance
C. Justify the business case
D. Procure hardware
E. Identify key performance indicators
F. Act as an approval authority

Question No : 393) A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned about losing access to the data. Which of the following documents is appropriate for use in this situation?
A. Project schedule
B. Risk register
C. Action item log
D. Issue log
Question No : 394) Language barriers will MOST likely influence a PM to:
A. use more print media to communicate with the stakeholders.
B. hire a bilingual project team that is fluent in the language to reduce conflict.
C. hire an interpreter to ensure verbal and written communications are accurate.
D. learn the unknown language to be able to communicate effectively with stakeholders.

Question No : 395) A project requires that laptops be obtained immediately. The project manager confirms existing laptops, which were used for a previous project, are available, but authorization is required to use them. Which of the following risk response strategies does this represent?
A. Exploit
B. Accept
C. Mitigate
D. Transfer

Question No : 396) A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint. Which of the following should the Scrum master do to improve the team's velocity in the next sprint?

A. Take a more hands-on leadership approach.
B. Add the unfinished work to the backlog.
C. Schedule a sprint retrospective.
D. Hold additional daily stand-up meetings.

Question No : 397) In which of the following circumstances would faxing be the MOST appropriate communication method?
A. When sending confidential information
B. When resolving complex issues
C. When providing weekly status updates
D. When signatures are required

Question No : 398) While working with a project team to create the project schedule, which of the following must occur for performance measurement?
A. Identify resource costs
B. Manage issues
C. Create status reports
D. Set the baseline

Question No : 399)The problem statement of a project helps to identify:
A. roadblocks impeding project progress
B. a connection to a larger program
C. a reason or purpose
D. start and end dates

Question No : 400) A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables. Which of the following steps should the project manager take to BEST resolve the issue?
A. Ask the project sponsor for shared resources for the key stakeholder’s project.
B. Ask the project sponsor for benched resources for the time-sensitive project.
C. Ask the key stakeholder for low-quality resources for the time-sensitive project.
D. Ask the project sponsor for dedicated resources for the time-sensitive project.

Question No : 401) Which of the following are major characteristics of sprint planning? (Choose two.)
A. Defining the sprint durations
B. Defining the sprint owners
C. Defining the sprint parameters
D. Defining the number of sprints
E. Defining the sprint classifications
Question No : 402) The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?
A. Projectized
B. Functional
C. Matrix
D. Intermediary

Question No : 403) A team member has been consistently underperforming, and mentoring has not corrected the problem. Which of the following actions should the project manager take?
A. Hire additional personnel.
B. Inform the project sponsor.
C. Replace the resource.
D. Send the resource to training.

Question No : 404) An organization is divided into three separate entities based on geographical region. Which of the following types of organizational change is this?
A. Relocation
B. Outsourcing
C. Demerger
D. Split
Question No : 405) A project has just begun, and people are not clear about the objectives. Which of the following meeting types is needed?
A. Stand-up
B. Scheduling
C. Impromptu
D. Kickoff
 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 29-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.