Question No : 466) A sprint retrospective is being conducted. Which of the following is the BEST way to obtain input?
A. Video conference
B. Face-to-face meeting
C. Instant messaging
D. Collaboration site
Question No : 467) An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?
A. Language barrier
B. Personal preference
C. Technological factor
D. Cultural difference
Question No : 468) A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule. Which of the following would the project manager most likely do NEXT?
A. Create a WBS.
B. Determine predecessors and dependencies.
C. Determine the critical path.
D. Prioritize tasks.
Question No : 469) A mandatory evacuation has been ordered due to a natural disaster. Which of the following should be applied?
A. Incident response plan
B. Business continuity plan
C. Business risk plan
D. Emergency plan
Question No : 470) Which of the following is a document that new employees at an organization sign as a condition of employment if they will be using the organization’s proprietary processes?
A. NDA
B. SLA
C. SOW
D. LOI
Question No : 471) A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented. Which of the following constraints has MOST likely been overlooked?
A. Scope
B. Resources
C. Environment
D. Quality
Question No : 472) A sensitive project requires activities to occur with very specific, to-the-minute timing. Which of the following would BEST ensure on-time delivery?
A. Text messaging
B. Face-to-face activity monitoring
C. Video conferencing
D. Voice conferencing
Question No : 473) An approved change was implemented. Which of the following should be accomplished NEXT?
A. Update the documentation.
B. Validate the change.
C. Update the project sponsor.
D. Validate the impact.
Question No : 474) A project manager recently joined a projectized organization and is having many issues on five different projects. Which of the following risk activities should be performed FIRST? (Choose two.)
A. Identify
B. Coordinate
C. Qualify
D. Brainstorm
E. Mitigate
F. Assign
Question No : 475) A company wants to remodel two areas in a building it is leasing. The company will utilize its own contractors to remodel the areas. The building owners agree to the remodel. Whichof the following documents would the owners MOST likely utilize with the business?
A. SWOT
B. RFQ
C. MOU
D. PO
Question No : 476) Which of the following tasks are responsibilities of the project manager role?
A. Provide inputs, estimate tasks, and manage a team
B. Manage the budget, perform quality assurance, and be accountable for artifacts
C. Set deliverables, control risk, manage risk, and create a project charter
D. Manage a team, marketing, roadblocks, and project steering
Question No : 477) To control costs, project funding is being released under a waved approach. After passing each milestone, the project receives the next round of funding. Which of the following is hindered by this funding approach?
A. Resource sharing
B. Crash schedule
C. Burn rate
D. Team outsourcing
Question No : 478)A construction company has not been on the job for more than two weeks. Which of the following is an example of how a project manager can utilize the transfer risk strategy?
A. Changing the schedule to accommodate a new finish date
B. Hiring a new company to complete the work
C. Calling the project sponsor to explain the situation
D. Requiring the construction company to send new employees
Question No : 479) A customer is in the early planning stages of a technology rebuild. To gain a better understanding of the possible solutions, which of the following documents should the customer send to prospective vendors?
A. RFP
B. RFQ
C. RFI
D. SOW
Question No : 480) A major project task involves purchasing and implementing computer equipment with special software, which is valued at $1.5 million, for a 700-employee organization. An IT department manager challenged the PM's ability to authorize expenditures after the purchase was made. Which of the following documents should the PM provide to the functional manager?
A. Organizational chart
B. Project charter
C. Cost management plan
D. Change management plan
PK0-005 Answers