Question No : 526) A project manager is collecting work package information from the project team for the first time.Which of the following elements should the project manager have at the end of the meeting?
A. Task name, duration, and dependencies
B. Task leveling, baseline, and critical path
C. Task assignments, quality requirements, and project governance sign-off
D. Task start, finish, and estimate cost
Question No : 527) Which of the following is the BEST method to provide quick status updates on project tasks without interrupting project activities?
A. Phone call
B. Interoffice mail
C. Newsletter
D. Internal collaboration site
Question No : 528) Company A and Company B have come together to form a new Company C. Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave. These are examples of: (Choose two.)
A. business reorganization
B. business relocation
C. business outsourcing
D. business merger
E. business process change
Question No : 529)During an active project, a meeting is set up to explain new internal processes. Which of the following MOST likely triggered this meeting?
A. The scope of the project changed.
B. The sponsor requested additional functionality.
C. A project team member left the organization.
D. The PMO standard requirements changed.
Question No : 530) Which of the following organization types requires the project manager to report performance issues to another department?
A. Functional
B. Strong matrix
C. Projectized
D. Weak matrix
Question No : 531) A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time. Which of the following BEST describes this scenario?
A. Score creep
B. Interactions between constraints
C. Constraint reprioritization
D. Change request
Question No : 532) A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?
A. Trust the contractor to do the job well because the company has been in business for a long time.
B. Tell the contractor that the company is responsible for any damage done to underground lines.
C. Immediately fix any broken lines that are hit during construction.
D. Ensure the contractor has the appropriate utility maps.
Question No : 533) During a project, the purpose of examining the cost baseline is to:
A. organize payment of the bills
B. determine the minimal cost of the project
C. anticipate the total planned costs
D. compare against the total planned income
Question No : 534) Which of the following documents would MOST likely provide a broad, non-customized overview of a product or service?
A. SLA
B. RFI
C. RFP
D. SOW
Question No : 535) While working on a project, a self-organized team determines what will be accomplished during the next two weeks. Which of the following describes what the team is doing?
A. Creating a WBS
B. Gathering continuous requirements
C. Sprint planning
D. Holding a Scrum meeting
Question No : 536) A functional manager pulled a resource from a current project to work on a higher-priority project but did not offer a backfill resource. Which of the following should the project manager do FIRST?
A. Report the project as at risk and share the issue with the project team.
B. Meet with the functional manager to discuss the issue.
C. Delay the task in the schedule and inform the sponsor.
D. Open a change request to reduce the project scope.
Question No : 537) Which of the following risk management activities identifies the severity of a risk event?
A. Quantification
B. Identification
C. Response
D. Mitigation
Question No : 538) A project manager wants to determine the percentage of a project's budgeted costs versus expenditures. Which of the following calculations should the project manager perform?
A. Burn rate
B. Critical path analysis
C. EV
D. EAC
Question No : 539) A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires.Which of the following is the BEST change control process to follow?
A. Identify, implement, approve, evaluate, validate, update, communicate
B. Identify, evaluate, approve, implement, validate, update, communicate
C. Identify, approve, evaluate, implement, validate, update, communicate
D. Identify, validate, evaluate, approve, implement, update, communicate
Question No : 540) During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire?
A. Status report
B. Task durations
C. Project schedule
D. Schedule management plan