Question No : 646)A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is the project manager performing?
A. Defining activities
B. Estimating activity resources
C. Developing a schedule
D. Sequencing activities
Question No : 647) A politically sensitive project is being proposed. The sponsor decides to outsource the work despite having a highly capable team. Which of the following BEST describes the risk mitigation strategy being used?
A. Acceptance
B. Avoidance
C. Transference
D. Exploitation
Question No : 648) A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?
A. Kickoff
B. Impromptu
C. Closure
D. Status
Question No : 649) A project manager is not receiving cooperation from a department that is vital to the success of a project. Because of this, the project cannot move forward. Which of the following is the BEST place the project manager should go to get help with this issue?
A. Project management office
B. Project stakeholders
C. Project team
D. Project sponsors
Question No : 650) A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?
A. Closing
B. Executing
C. Planning
D. Monitoring and controlling
Question No : 651) A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A. Submit a change request to the CCB.
B. Implement the change to the project.
C. Determine the impact of the requested change.
D. Update the schedule to accommodate the change.
Question No : 652) While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources based upon priorities, and optimizing resource deployment between projects. Which of the following BEST describes these actions?
A. Portfolio management
B. Agile management
C. Project management
D. Strategic management
Question No : 653) A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account:
? Delivery
? Vacation
? Cost of overtime
? Work effort
Which of the following documents should the project manager use to guarantee the project’s success?
A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart
Question No : 654) A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
A. risk owner
B. risk impact
C. risk review
D. risk trigger
Question No : 655) A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:
A. RTM
B. RFQ
C. RFI
D. RFP
Question No : 656) The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)
A. Scope creep
B. Deliverables
C. Business requirements
D. Project schedule
E. Gate review
F. Key performance indicators
Question No : 657) In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
A. a dedicated resource pool
B. an allocated resource pool
C. a shared resource pool
D. a benched resource pool
Question No : 658) A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?
A. Project schedule
B. Issue log
C. Risk register
D. Scope statement
Question No : 659) A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
A. Timeline
B. Quality
C. Budget
D. Scope
Question No : 660) A vendor is late with product deliverables. Which of the following documents should the PM refer to FIRST?
A. C&D letter
B. MOU
C. SLA
D. SOW