Question No : 646)A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is the project manager performing?
A. Defining activities
B. Estimating activity resources
C. Developing a schedule
D. Sequencing activities

Question No : 647) A politically sensitive project is being proposed. The sponsor decides to outsource the work despite having a highly capable team. Which of the following BEST describes the risk mitigation strategy being used?
A. Acceptance
B. Avoidance
C. Transference
D. Exploitation

Question No : 648) A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?
A. Kickoff
B. Impromptu
C. Closure
D. Status
Question No : 649) A project manager is not receiving cooperation from a department that is vital to the success of a project. Because of this, the project cannot move forward. Which of the following is the BEST place the project manager should go to get help with this issue?
A. Project management office
B. Project stakeholders
C. Project team
D. Project sponsors

Question No : 650) A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?
A. Closing
B. Executing
C. Planning
D. Monitoring and controlling

Question No : 651) A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A. Submit a change request to the CCB.

B. Implement the change to the project.

C. Determine the impact of the requested change.

D. Update the schedule to accommodate the change.

Question No : 652) While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources based upon priorities, and optimizing resource deployment between projects. Which of the following BEST describes these actions?
A. Portfolio management
B. Agile management
C. Project management
D. Strategic management

Question No : 653) A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account:
? Delivery
? Vacation
? Cost of overtime
? Work effort
Which of the following documents should the project manager use to guarantee the project’s success?
A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart
Question No : 654) A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
A. risk owner
B. risk impact
C. risk review
D. risk trigger

Question No : 655) A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:
A. RTM
B. RFQ
C. RFI
D. RFP

Question No : 656) The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)
A. Scope creep

B. Deliverables

C. Business requirements

D. Project schedule

E. Gate review

F. Key performance indicators

Question No : 657) In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
A. a dedicated resource pool
B. an allocated resource pool
C. a shared resource pool
D. a benched resource pool

Question No : 658) A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?
A. Project schedule
B. Issue log
C. Risk register
D. Scope statement

Question No : 659) A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
A. Timeline

B. Quality

C. Budget

D. Scope

Question No : 660) A vendor is late with product deliverables. Which of the following documents should the PM refer to FIRST?
A. C&D letter
B. MOU
C. SLA
D. SOW
 

PK0-005 Answers

 

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

Part 7

Part 8

Part 9

Part 10

Part 11

Part 12

Part 13

Part 14

Part 15

Part 16

Part 17

Part 18

Part 19

Part 20

Part 21

Part 22

Part 23

Part 24

Part 25

Part 26

Part 27

Part 28

Part 29

Part 30

Part 31

Part 32

Part 33

Part 34

Part 35

Part 36

Part 37

Part 38

Part 39

Part 40

Part 41

Part 42

Part 43

Part 44

Part 45

Part 46

Part 47

Logo

Our goal is to help students clear their exam by providing them genuine questions which helps students to achieve their goal. Many students have cleared their exam by going through our courses. Are you ready to clear yours?


Site Secured

mcaafe-secure

Last Scanned: 29-05-2025

Links

  • FAQ
  • Money Back Guarantee
  • About Us
  • Privacy Policy
  • Terms & Conditions
  • Contact Us
  • Testimonials

Disclaimer

  • SAP, Microsoft, Google, Amazon, Qualtrics, and all other brands are Registered Trademarks of their respective companies.
  • Theexamquestions.com is no way affiliated With any brand hosted on this website.
  • Theexamquestions.com offers only probable exam questions and answers.
  • Theexamquestions.com offer learning materials and practice tests created by subject matter technology experts to assist and help learners prepare for those exams. Theexamquestions.com do not offer dumps or questions from the actual exam.
  • Theexamquestions.com does not own or claim any ownership on any of the brands.
  • All Certification Brands used on the website are owned by the respective brand owners.

All course contents, trademarks, service marks, trade names, product names and logos appearing on the site are the property of their respective owners. The website Theexamquestions.com is in no way affiliated with any of the certification providers. Copyright © 2025 www.theexamquestions.com. All rights reserved.